Falcon delivery plan

This is the team's working view of the roadmap. The README roadmap is the customer view; it changes only when a milestone changes status or date. This page carries the detail that changes week to week: work packages, decision gates, risks, and tracker housekeeping.

Source of truth: GitHub milestones for milestone names and target dates; the issues for scope and acceptance criteria. Work windows inside a milestone are planning estimates made on 29 Oct 2026 from the dependencies in the execution strategy, milestone execution matrix and M1 plan. They are not owner-approved commitments.

Last updated: 29 Oct 2026.

Status snapshot

Milestone Target Status Open / total issues
M0 — Competitive evidence baseline 13 Nov 2026 Done 0 / 3
M1 — Trustworthy Alpha 8 Jan 2027 Issues closed 10 Nov 2026; exclusions listed below 0 / 4
M2 — Secure Technical Preview 19 Feb 2027 Waiting on owner decision and reviewer 3 / 3
M3 — Verified Self-Healing 26 Mar 2027 Planned 3 / 3
M4 — Developer Beta 7 May 2027 Planned 3 / 3
M5 — Efficient CI 18 Jun 2027 Planned 3 / 3
M6 — Enterprise Operations 13 Aug 2027 Planned 4 / 4
M7 — Customer Pilot 24 Sep 2027 Planned 3 / 3
M8 — Advanced QA 3 Dec 2027 Planned 3 / 3
M9 — Independent Competitive Release 14 Jan 2028 Planned 3 / 3

Five evidence-gap issues (#113–#117) are open with no milestone.

Full delivery chart

All milestones, work packages and decision gates in one view. Red bars are the critical path: a slip there moves the milestone date. Diamonds are milestone targets and decision or review gates. [BLOCKED] marks work that cannot start until a gate clears.

gantt
    title Falcon delivery plan with decision gates (29 Oct 2026)
    dateFormat  YYYY-MM-DD
    axisFormat  %b %Y
    tickInterval 2month
    todayMarker off

    section M0
    #74 Competitor evidence register             :done,    m0a, 2026-10-23, 2026-10-27
    #75 Neutral benchmark harness                :done,    m0b, 2026-10-23, 2026-10-27
    #76 Capability truth table                   :done,    m0c, 2026-10-24, 2026-10-27
    M0 due 13 Nov (closed 26 Oct)                :milestone, done, m0d, 2026-11-13, 0d

    section M1
    WP-79a Verification classifier (#79)         :done,    w79a, 2026-10-27, 1d
    WP-79s Shard carriage (#79)                  :done,    w79s, 2026-10-27, 1d
    WP-77a Contract schema + store (#77)         :done,    w77a, 2026-10-27, 1d
    #125 ContractStore hardening                 :done,    h125, 2026-10-28, 1d
    GATE Owner decisions D2 D3 D8                :milestone, g1, 2026-11-06, 0d
    WP-77b entry conditions (from #125)          :done, crit, e77b, 2026-11-02, 2026-11-14
    WP-78a State-graph model + guard (#78)       :done,    w78a, 2026-11-02, 2026-11-10
    WP-77b Stage A evaluator (#77)               :done, crit, w77b, 2026-11-16, 2026-12-05
    WP-77d Proposal + approval UX (#77)          :done,    w77d, 2026-11-23, 2026-12-19
    G-03 #115 Allure content assertion           :         g03,  2026-11-23, 2026-12-03
    WP-77c Business fixtures (#77)               :done,    w77c, 2026-12-07, 2026-12-19
    WP-79b CLI dashboard Allure (not delivered)  :crit,    w79b, 2026-12-07, 2026-12-19
    WP-78b SiteSweep integration (not delivered) :crit,    w78b, 2026-12-14, 2027-01-02
    WP-M1Q Qualification + reviews               :crit,    m1q,  2027-01-04, 2027-01-09
    Customer discovery track D6 (non-gating)     :         d6,   2026-11-09, 2027-02-20
    M1 due 8 Jan                                 :milestone, m1d, 2027-01-08, 0d

    section M2
    G-01 #113 Real Firefox/WebKit launch         :         g01,  2027-01-11, 2027-01-16
    G-02 #114 TLS PostgreSQL in CI               :         g02,  2027-01-18, 2027-01-23
    #80 Phase 18 security gates [BLOCKED]        :crit,    i80,  2027-01-11, 2027-01-30
    GATE OWNER-24/25 browser posture             :milestone, g2, 2027-01-22, 0d
    #81 Safe autonomous action policy            :crit,    i81,  2027-01-25, 2027-02-11
    #82 Isolated auth journeys [BLOCKED]         :crit,    i82,  2027-02-01, 2027-02-18
    GATE Independent human security sign-off     :milestone, g3, 2027-02-18, 0d
    M2 due 19 Feb                                :milestone, m2d, 2027-02-19, 0d

    section M3
    G-04 #116 Opt-in live provider checks        :         g04,  2027-02-22, 2027-03-04
    #83 Healing benchmark corpus                 :crit,    i83,  2027-02-22, 2027-03-06
    G-05 #117 External-app healing accuracy      :         g05,  2027-03-01, 2027-03-13
    #84 Matching + replay invariants             :crit,    i84,  2027-03-08, 2027-03-20
    #85 Repair explainability + rollback UX      :         i85,  2027-03-15, 2027-03-27
    M3 due 26 Mar                                :milestone, m3d, 2027-03-26, 0d

    section M4
    #86 Playwright TS import + inventory         :crit,    i86,  2027-03-29, 2027-04-17
    #87 Playwright export + migration proofs     :crit,    i87,  2027-04-12, 2027-05-04
    #88 Five-minute onboarding                   :         i88,  2027-04-19, 2027-05-08
    M4 due 7 May                                 :milestone, m4d, 2027-05-07, 0d

    section M5
    #89 Change-impact test selection             :crit,    i89,  2027-05-10, 2027-05-29
    #91 Execution + AI-cost budgets              :         i91,  2027-05-10, 2027-06-05
    #90 Failure clustering + triage notes        :crit,    i90,  2027-05-31, 2027-06-19
    M5 due 18 Jun                                :milestone, m5d, 2027-06-18, 0d

    section M6
    #92 RBAC + actor-attributed review           :crit,    i92,  2027-06-21, 2027-07-17
    #93 (+#94 dup) Retention + audit export      :         i93,  2027-07-05, 2027-07-31
    #95 CI integrations + multi-project          :crit,    i95,  2027-07-19, 2027-08-12
    GATE Human security review                   :milestone, g4, 2027-08-12, 0d
    M6 due 13 Aug                                :milestone, m6d, 2027-08-13, 0d

    section M7
    #98 Packaging + support policy (legal)       :         i98,  2027-08-16, 2027-09-11
    #96 Three design-partner evaluations         :crit,    i96,  2027-08-16, 2027-09-25
    #97 ROI / TCO calculator                     :         i97,  2027-08-23, 2027-09-18
    M7 due 24 Sep                                :milestone, m7d, 2027-09-24, 0d

    section M8
    #99 Accessibility audits in journeys         :         i99,  2027-09-27, 2027-10-30
    #100 Visual regression baselines             :         i100, 2027-10-11, 2027-11-13
    #101 API/UI correlation                      :crit,    i101, 2027-10-25, 2027-12-02
    M8 due 3 Dec                                 :milestone, m8d, 2027-12-03, 0d

    section M9
    #102 Cross-product benchmarks                :         i102, 2027-12-06, 2027-12-24
    #103 Independent security + QA review [BLOCKED] :crit, i103, 2027-12-06, 2028-01-08
    #104 Release readiness dossier               :crit,    i104, 2028-01-03, 2028-01-15
    M9 due 14 Jan 2028                           :milestone, m9d, 2028-01-14, 0d
Loading

Critical path

  • M1: WP-77b entry conditions → WP-77b evaluator → WP-79b strict CLI and reporting → WP-78b discovery in SiteSweep → M1 qualification. It has zero float, and WP-78b falls over the holidays.
  • M2: #80 security gates → #81 safe-action policy → #82 isolated authenticated journeys. Gated by OWNER-24/25 and by an independent human security sign-off.
  • First externally defensible claim: #79 → #77 → #83 with external applications (#117) → #102.

Decisions needed

Decision Owner Needed by Blocks
D2 · Treat #77 Stage A as the first slice of Phase 19 CTO 6 Nov 2026 WP-77d
D3 · Limit #78 in M1 to unauthenticated, same-origin fixture journeys CTO 6 Nov 2026 WP-78b, #78 closure
D8 · Default exit code for zero-assertion runs CTO 6 Nov 2026 WP-79b, M1 qualification
OWNER-24/25 · Supported browser posture for authenticated runs CTO 22 Jan 2027 #82, M2, authenticated pilots in M7
Contract an independent human security reviewer CTO Nov 2026 M2 (#80), M6, M9 (#103)
D6 · Non-gating customer discovery track from M1 CTO Nov 2026 Early validation before M7

Tracker housekeeping

Item Proposed action
#79 closed on 27 Oct, but WP-79b (strict --require-verified, dashboard and Allure agreement) is not in the code Reopen #79, or open a WP-79b issue under M1
#94 duplicates #93 Copy #94's extra criteria into #93, then close #94
Evidence gaps #113–#117 have no milestone Assign G-03 (#115) to M1, G-01 (#113) and G-02 (#114) to M2, G-04 (#116) and G-05 (#117) to M3

Milestone detail

Each chart shows the milestone's issues, including proposed evidence-gap issues. Waiting (red) marks work blocked on an owner decision or an independent reviewer.

M0 — Competitive evidence baseline · target 13 Nov 2026 · Done

Done when: Completed on 26 Oct 2026. The competitor evidence register, the benchmark harness with a local run, and the capability truth table are published.

Depends on: Nothing

gantt
    title M0 Competitive evidence baseline, due 13 Nov 2026
    dateFormat YYYY-MM-DD
    axisFormat %d %b
    tickInterval 1day
    todayMarker off

    section Done
    Competitor evidence register (#74)                  :done, t1, 2026-10-23, 2026-10-27
    Neutral benchmark harness (#75)                     :done, t2, 2026-10-23, 2026-10-27
    Capability truth table and claim audit (#76)        :done, t3, 2026-10-24, 2026-10-27
Loading

M1 — Trustworthy Alpha · target 8 Jan 2027 · Issues closed 10 Nov 2026

Status update, 10 Nov 2026: #79, #125, #77 and #78 are closed. #78 delivered the JourneyExplorer library only: no CLI flag, no SiteSweep integration, no real-site validation, no form-entry or login exploration. Strict --require-verified mode (WP-79b) is not in the code. The status table and the README chart reflect this. The M1 bars for the closed issues (#77, #78, #125) are now marked done in both charts below. Their planned dates are the 29 Oct plan and were not re-baselined, and the two follow-ups that were not delivered (WP-79b, WP-78b) keep their original dates; future milestones are not replanned.

Done when: A run with no approved business checks can never be reported as fully verified. Approved checks run the same way every time, without an LLM. Discovery finds 2–5 step journeys in local test apps, within set page and action limits.

Depends on: M0

gantt
    title M1 Trustworthy Alpha, due 8 Jan 2027
    dateFormat YYYY-MM-DD
    axisFormat %d %b
    tickInterval 2week
    todayMarker off

    section Done
    Foundations merged (#79, #77, #125)                 :done, t1, 2026-10-23, 2026-10-29
    Contract store follow-ups (#125)                    :done, t2, 2026-11-02, 2026-11-14
    Journey discovery library (#78)                     :done, t3, 2026-11-02, 2026-11-10
    Business assertion evaluator (#77)                  :done, t4, 2026-11-16, 2026-12-05
    Assertion review and approval (#77)                 :done, t5, 2026-11-23, 2026-12-19

    section Planned
    Allure report check (#115, proposed)                :t6, 2026-11-23, 2026-12-03
    Strict CLI, dashboard, Allure (#79 follow-up)       :t7, 2026-12-07, 2026-12-19
    Discovery in SiteSweep (#78)                        :t8, 2026-12-14, 2027-01-02
    Milestone qualification and reviews                 :t9, 2027-01-04, 2027-01-08
Loading

M2 — Secure Technical Preview · target 19 Feb 2027 · Waiting on owner decision and reviewer

Done when: Destructive actions are blocked by default, with a visible reason. Each user role runs in its own browser context, with no shared sessions or leaked secrets. An independent human security review signs off.

Depends on: M1, and an independent security reviewer

gantt
    title M2 Secure Technical Preview, due 19 Feb 2027
    dateFormat YYYY-MM-DD
    axisFormat %d %b
    tickInterval 1week
    todayMarker off

    section Waiting
    Phase 18 security gates (#80)                       :crit, t1, 2027-01-11, 2027-01-30
    Isolated authenticated journeys (#82)               :crit, t2, 2027-02-01, 2027-02-18

    section Planned
    Firefox and WebKit launch test (#113, proposed)     :t3, 2027-01-11, 2027-01-16
    TLS PostgreSQL in CI (#114, proposed)               :t4, 2027-01-18, 2027-01-23
    Safe autonomous action policy (#81)                 :t5, 2027-01-25, 2027-02-11
Loading

M3 — Verified Self-Healing · target 26 Mar 2027 · Planned

Done when: Healing accuracy, wrong-action and refusal rates are published reproducibly, including on applications the Falcon team did not write. Ambiguous matches are refused, and every repair can be traced and undone.

Depends on: M0 and M1

gantt
    title M3 Verified Self-Healing, due 26 Mar 2027
    dateFormat YYYY-MM-DD
    axisFormat %d %b
    tickInterval 1week
    todayMarker off

    section Planned
    Opt-in live provider checks (#116, proposed)        :t1, 2027-02-22, 2027-03-04
    Healing benchmark corpus (#83)                      :t2, 2027-02-22, 2027-03-06
    Healing accuracy on external apps (#117, proposed)  :t3, 2027-03-01, 2027-03-13
    Matching and replay invariants (#84)                :t4, 2027-03-08, 2027-03-20
    Repair explainability and rollback (#85)            :t5, 2027-03-15, 2027-03-27
Loading

M4 — Developer Beta · target 7 May 2027 · Planned

Done when: Playwright suites import without running their code, and anything unsupported is listed rather than skipped. Exported tests compile and pass. A first run works on Node.js 22 and 24 without an API key.

Depends on: M1 and M3

gantt
    title M4 Developer Beta, due 7 May 2027
    dateFormat YYYY-MM-DD
    axisFormat %d %b
    tickInterval 1week
    todayMarker off

    section Planned
    Playwright TypeScript import (#86)                  :t1, 2027-03-29, 2027-04-17
    Playwright export and migration proofs (#87)        :t2, 2027-04-12, 2027-05-04
    Five-minute onboarding (#88)                        :t3, 2027-04-19, 2027-05-08
Loading

M5 — Efficient CI · target 18 Jun 2027 · Planned

Done when: If the impact of a change is unknown, the full relevant test set runs. A run that hits its budget reports PARTIAL or UNKNOWN, never PASSED. Related failures are grouped without hiding different root causes.

Depends on: M1

gantt
    title M5 Efficient CI, due 18 Jun 2027
    dateFormat YYYY-MM-DD
    axisFormat %d %b
    tickInterval 1week
    todayMarker off

    section Planned
    Change-impact test selection (#89)                  :t1, 2027-05-10, 2027-05-29
    Execution and AI-cost budgets (#91)                 :t2, 2027-05-10, 2027-06-05
    Failure clustering and triage notes (#90)           :t3, 2027-05-31, 2027-06-19
Loading

M6 — Enterprise Operations · target 13 Aug 2027 · Planned

Done when: Access is denied by default, and audit records show who did what. Retention, deletion and audit export are integrity-checked, with no credentials or personal data in default artifacts. CI integrations are safe for pull requests from forks.

Depends on: M2, and an independent security review

gantt
    title M6 Enterprise Operations, due 13 Aug 2027
    dateFormat YYYY-MM-DD
    axisFormat %d %b
    tickInterval 1week
    todayMarker off

    section Planned
    RBAC and attributed reviews (#92)                   :t1, 2027-06-21, 2027-07-17
    Retention and audit export (#93, #94)               :t2, 2027-07-05, 2027-07-31
    CI integrations and multi-project (#95)             :t3, 2027-07-19, 2027-08-12
Loading

M7 — Customer Pilot · target 24 Sep 2027 · Planned

Done when: Three scoped design-partner evaluations are completed, or the reason they could not be recruited is documented. ROI figures use customer-verified inputs. Packaging decisions have legal sign-off.

Depends on: M2, M3, and recruiting design partners

gantt
    title M7 Customer Pilot, due 24 Sep 2027
    dateFormat YYYY-MM-DD
    axisFormat %d %b
    tickInterval 1week
    todayMarker off

    section Planned
    Packaging and support policy (#98)                  :t1, 2027-08-16, 2027-09-11
    Three design-partner evaluations (#96)              :t2, 2027-08-16, 2027-09-25
    ROI and TCO calculator (#97)                        :t3, 2027-08-23, 2027-09-18
Loading

M8 — Advanced QA · target 3 Dec 2027 · Planned

Done when: Accessibility findings are tied to journeys and never presented as certification. Visual baselines change only with explicit approval. UI actions are linked to API evidence, with sensitive data masked.

Depends on: M1 and M6

gantt
    title M8 Advanced QA, due 3 Dec 2027
    dateFormat YYYY-MM-DD
    axisFormat %d %b
    tickInterval 2week
    todayMarker off

    section Planned
    Accessibility audits in journeys (#99)              :t1, 2027-09-27, 2027-10-30
    Visual regression baselines (#100)                  :t2, 2027-10-11, 2027-11-13
    API and UI correlation (#101)                       :t3, 2027-10-25, 2027-12-02
Loading

M9 — Independent Competitive Release · target 14 Jan 2028 · Planned

Done when: The benchmark is rerun on the release version. An independent human security and QA review is recorded. Every published claim links to its evidence.

Depends on: All earlier milestones, and independent reviewers

gantt
    title M9 Independent Competitive Release, due 14 Jan 2028
    dateFormat YYYY-MM-DD
    axisFormat %d %b
    tickInterval 1week
    todayMarker off

    section Waiting
    Independent security and QA review (#103)           :crit, t1, 2027-12-06, 2028-01-08

    section Planned
    Cross-product benchmarks (#102)                     :t2, 2027-12-06, 2027-12-24
    Release readiness dossier (#104)                    :t3, 2028-01-03, 2028-01-15
Loading

Top risks

Risk Impact Mitigation
WP-78b (size L) lands over the holidays with zero float M1 slips 1–2 weeks Start WP-78a now beside the WP-77b entry conditions; move WP-78b's replay-evidence slice into M1 qualification if needed
Review capacity: every work package needs independent QA, code review and, where triggered, security review Merges queue up Keep at most two tasks in flight; book review slots weekly
Owner-decision latency (D2, D3, D8, OWNER-24/25) Blocks the end of M1 and all of M2 Dated gates on the chart
No independent human security reviewer contracted M2, M6 and M9 stay NO-GO Start procurement in November 2026
First customer contact is in M7 Late validation of the core thesis Run the non-gating discovery track (D6) from November 2026